Headed back to the work cabin in the morning, on the truck rack is the ship lap boards I need to finish the ceiling, there are 137- 6”x12’ boards plus the 30 or so already there, to be cut 22-1/4” and nailed between the trusses to form the open beam look. My phone calculator says that’s 842 pieces. If I can average 1 minute ea. to cut and nail on, it’s 14 hours, in reality it will be at least 3 days, but first I have to finish staining all the beams, that’s another day or two. Should be able to complete the ceiling and get a good start on the walls this trip. I can post from there but don’t have enough internet to post pictures, so I’ll post the pictures in a couple weeks.